Principal Projects Manager

Principal Projects Manager

Work Experience

OBJECTIVE

Senior Projects Management / Business Development / Commercial, Contractual and Legal Affairs & Administration


PRESENT: WINTERSHALL NOORDZEE B.V.
PRINCIPAL PROJECTS MANAGER

Responsible for the field development of two significant developments within the Dutch sector.
D15-FA1: - COMPLETED
Based in The Hague to drive the execution from the initial FEED concept, concluding at EPIC award. Responsible for the preparation of all EPC & T&I Tender Contracts, Partner approvals, unitization agreements, Project Sanction thru to eventual Project Award and subsequent development, installation and start-up of the D15-FA-1 gas field.

L8-P4: - Completed May 2001
Responsible for the development of the L8-P4 gas field, responsibility details as above

Both of these projects are in excess of 100 MM. For which I have full project management and budget responsibility, and total accountability for the execution of the project.

Sound knowledge of UK and European Government policies and legislation, in particular significant in-depth knowledge of Dutch legislation.


1995 - 1997: AMOCO (UK) EXPLORATION COMPANY
PROJECT MANAGER

Responsible for the development of `new concepts’ Southern North Sea Marginal Fields
Reporting to the Projects General Manager for the initiation of feasibility, concept, design and eventual fabrication & installation for new SNS marginal fields using innovative technology.

Total budget responsibility and negotiation authority with all third parties, responsible for interfacing with, and seeking approvals from Regulatory and Government Bodies.


1994 - 1995: SHELL U.K. EXPLORATION & PRODUCTION
PROJECT MANAGER

Assigned to the Barque PB Revamp - de-manning Project to drive the execution of all activities associated with the rationalisation of the SFU Leman Gas Field Project

Responsible for the development and progress options from feasibility, thru implementation, ensuring budget and project schedules are met by proposing cost-effective strategies employing \"brown field\" philosophy. Based on the original Technical and Feasibility Studies, responsible for the preparation of the Basis of Conceptual, and subsequent Detailed Designs, development of appropriate strategies Ensuring Project reviews are correctly applied, and the most cost effective offshore implementation followed

Responsible for the review of: Engineering design, & development of the Topsides facilities.
Management of the Engineering Contractors during conceptual/detailed design, & follow-on engineering.
Preparation for, and participation in, Technical Audits acting as facilitator, Presenting development strategies to the Health and Safety Executive, and seeking approvals from the Department of Trade and Industry.
Overall responsibility for developing and monitoring both the Engineering and Construction budget based on \"Business Unit\" Management


1992 - 1994: ELF PETROLAND B.V. DEN HAAG NETHERLANDS
COMPANY / PROJECT REPRESENTATIVE

Assigned to the Development of the K5A K5P & K5D Gas Field Project which features a 3 Well two platform central complex consisting of drilling, riser and production platforms, and the installation of a 12\" rough gas line linked to a satellite platform

Based in the Engineering Design Consultants office to Project Manage the Engineering Design Consultants Project Team performance on a \"fast track\" contract with respect to the Engineering Philosophy, Studies, Detailed Design, Installation and Hook-up Scope.
Responsible for the Consultants workscope including technical review and approval of all Engineering design documentation, progress and quality.

Total budget responsibility based on \"Business Unit\" management for the Design, Execute and implementation phases of the development including negotiations of Variation to scope, preparation and close-out
Technical review of Call for Tender Documents for the award of the fabrication contract.
Approval / verification of all Vendor documentation for Company supplied LLI
Preparation and approval of dossiers for licence application to relevant Government Authorities
Safety studies including HAZOP review/recommendations

1990 - 1992: AMOCO (UK) EXPLORATION COMPANY
PROJECT / CONSTRUCTION MANAGER - ONSHORE TERMINAL

Assigned to the Central Area Transmission System (CATS) Onshore Terminal Construction, Seal Sands Teesside which is the receiving and metering station for the Central Graben Gas Gathering Complex

Based initially in the Engineering Design Contractors office responsible for the Technical review and approval of all Engineering documentation prior to mobilisation to the Construction site. Responsible for the development and construction of the onshore receiving, metering and control facilities from a \"green field\" site.
Overall responsibility for the Contractor during the construction, installation, testing and commissioning phases of the Terminal facilities including the installation of 36\" CATS pipeline
Onshore pre and post commission and offshore subsea tie-in to the Amoco Everest and Lomond Riser Platforms to bring the plant on-stream. Responsible for the Selection and approval of all Sub Contractors and Vendors Negotiation and approval of design and subsequent construction changes
Total budget responsibility for both Engineering and Construction, and negotiation of variation costs


1989 - 1990: AMERADA HESS LIMITED
PROJECT INTERFACE MANAGER

Assigned to the \"Scott Field\" Development based in the Engineering Design Office, London.
Management of the Engineering Design Contractor for all design and development related work associated with a \"fast track\" EPIC Contract for Subsea Manifolds, Pipelines, Substructures & Topsides

Responsible for the Engineering Interface Department co-ordinating all Interface activities at Fabrication. Sites,
Review and approval of Engineering/Site Queries and Site Concessions, Dimensional Control. Team Leader responsible for Safety studies/investigations HAZOP recommendations and ANNEX B approvals.


1988 - 1989: NAM ASSEN NETHERLANDS
PROJECT DEVELOPMENT MANAGER

Based in Assen, The Netherlands, Responsible for the Project Development of Corporate Level activities for land based and offshore projects including:

Feasibility and conceptual design of proposed developments.

Quality Management: Lead Assessor in the development and implementation of ISO 9000 series. Process analysis, and system development. Project economics and budget control. Rationalisation of Standard Contracting Procedures and Articles of Agreement. Involved in HAZOP studies/investigations


1986 - 1988: BRITISH GAS PLC ROUGH STORAGE PROJECT
PROJECT MANAGER

Responsible for the co-ordination of all Field related activities for the Rough Storage Injection and Production Platforms.
Responsible to the Technical and Operations Manager for all onshore and offshore Field control and development, functional cost and progress reporting, policy implementation, budget control and projections for the overall Section Management.


OFFSHORE PROJECT CO ORDINATOR

Assigned offshore for the \"Amethyst tie-in Project\" responsible to the OIM for the Engineering Interface between BGC/BP for the pipeline tie-in.
Responsible for the implementation task force for the projection and development of future Fields, Team leader for Safety studies and HAZOP recommendations


1985 - 1986: AMOCO EXPLORATION UK LIMITED
PROJECT MANAGER

Based initially in the Engineering Design Contractors office responsible for the review and approval of all Engineering drawings and specifications prior to mobilisation to the Construction Site for the Bacton Phase II Terminal Expansion Project.

Responsible for the re-development and construction of the onshore receiving, metering and control facilities on a \"brown field\" site. Control and management of the Project from bid evaluation through selection of main contractor including construction, site supervision/manpower onshore test and pre-commissioning. Post-commissioning, site compilations and Project close out.
1984 - 1985: T H C CONSTRUCTION LIMITED
PROJECT MANAGER

Fabrication and construction of the Shell \"Indie N\" Jacket, Piles and Topsides.
Responsible to the Client for the control and management of all Project related activities.
Controlling and reporting progress on engineering, material procurement, fabrication, installation, quality assurance, quality control, certification and testing. Preparation and co-ordination of load out and sail-away including hand over to the hook-up contractors. Project close out.

HENLEY MANAGEMENT COLLEGE - PROJECT MANAGEMENT APPLICATION

1982 - 1984: CHARLTON LESLIE OFFSHORE LIMITED
ENGINEERING/TECHNICAL MANAGER

Responsible for the Engineering Co-ordination/control during the construction phase of the following projects: Marathon Oil Brae B Power Generation Modules - M08 Ml8 M28: BP Ula Field Separation and Compression Modules - PO1 PO2: Shell UK South East Indie Satellite Platforms - RM1 DM1

Responsibilities included the operation and control of the Engineering Design Office and Installation Contractor. Selection, co-ordination and supervision of transportation and load-out Contractors for the above modules, including preparation for sailaway and hand-over to hook-up & commissioning contractors. Liaison with Offshore installations group for Engineering Completion\'s

1980 - 1982: OTTO SIMON CARVES LIMITED
RESIDENT ENGINEER

Reporting to the Site Manager for the construction and commissioning of a multi million
Pound Refractory Rebuild/By-products Extension Plant for B.S.C. Cleveland.
Areas of responsibility included: Supervision of on-site Engineering design modifications, sub contractors, site inspection, progress reporting, material procurement and control, quality assurance. Preparation and supervision of punch listed items and acceptance documentation for vendor payments. Responsible for monitoring and reporting progress to the Client and site supervision throughout the commissioning phases.


1978 - 1980: BADGER B.V. DEN HAAG NETHERLANDS
SENIOR PROJECT ENGINEER

Assigned to the Joint Venture Project with Chiyoda Japan for the Wangerae Refinery Revamp New Zealand, for Shell International Netherlands, Project responsibilities included:
Preparation of proposals for tender packages, Tender evaluation and recommendations, Detailed engineering studies, Co-ordination of PEF & PEUF, and Control of Vendor documentation.


SENIOR PROJECT CO-ORDINATOR

HQ Construction department co-ordinating between The Netherlands, Japan, New Zealand, for the design of the Hydrocracking Plant and associated equipment. Scheduling offsite equipment for the development of site facilities, construction of roll-on/roll-off jetty in preparation for heavy lift items, and transportation to site.


1977 – 1978: WEST AUSTRALASIA PTY
ENGINEERING DESIGN CO-ORDINATOR

Seconded to Sydney Australia for a twelve month period for the development of an in-house Design Department for potential Oil Related Projects during development of the North West Shelf.


1976 - 1977: BRYTEK ENGINEERS LTD ON SECONDMENT TO THE FOLLOWING COMPANIES:

PROJECT ENGINEER: MAPLE NORWAY - ONSHORE/OFFSHORE.
SITE ENGINEER: CHARLTON LESLIE OFFSHORE.
TASK ENGINEER: BRYTEK GERMANY.


[1973 - L976]: ENGINEERING STUDIES
Full time studies / sandwich course first and final years Engineering Degree


1968 - 1974: IMPERIAL CHEMICALS LIMITED
FIVE YEAR APPRENTICESHIP

Three years design drawing office, two years on-plant training in Butadiene, Plastic and Monomer Plants, covering all aspects of design, construction and production of Major Chemical Plants.
Preparation of process engineering and utility flow diagrams and operational specifications.


Education

EDUCATION & QUALIFICATIONS

MA - H.S. Environmental & European Law (currently studying)
BSc - Engineering


PROFESSIONAL INSTITUTIONS / SPECIFIC RECOGNITION’S:

Business Woman of The Year - 1996
Member Institute of Project Management - 1989
Member Women’s Engineering Society - 1979

SUMMARY OF EXPERIENCE:

A very experienced professional having worked as a Consultant for major Operators throughout the UK and Europe, with some 25+ years significant experience in contractual, commercial project management & controls and legal affairs including that of mediator and arbitrator, together with sound knowledge of UK and European Government policies and legislation.

In particular has been responsible for the direction and implementation of several significant developments in an environment where the principals and practices of Total Quality Management have been pioneered through effective teamwork and dedicated leadership necessary to plan and execute intricate programmes.


PROFESSIONAL EXPERIENCE:

Total of 25+ year’s operational experience in:

Fixed Oil & Gas Platforms
Onshore Gas Terminals
Future Exploration/Field Development
Topsides Facilities
Subsea Developments
Integrated Decks
FPV - New Build
Petrochemical Complexes


COURSES/PRESENTATIONS/PUBLICATIONS:

Project Management Application
Project Management Workshop
Project Completion
Planning Techniques
Risk Analysis
Cost/Budget Control
Safety Case Application
Total Quality Management
Lead Assessor - Corrective Action Team